WOLLHEIM, J.
The dispute here is a familiar one: a construction defect action by a homeowners association against the developer and general contractor, who then filed third-party complaints against the multiple subcontractors. Most, but not all, of the claims settled. The claims of the developer and general contractor, La Noue Development, LLC (La Noue), against several subcontractors went to trial. Although La Noue prevailed, the jury awarded limited damages. This appeal relates to La Noue's claims against one subcontractor, Sharabarin, dba Advanced Construction, who installed the siding and trim on four of the townhouses that are the subject of this action. La Noue raises six assignments of error on appeal. Because we conclude that instructional error entitles La Noue to a new trial limited to damages, we reverse and remand for that reason and do not address La Noue's second assignment of error, relating to the trial court's denial of its motion for a new trial based on newly discovered evidence. However, we address the other assignments of error because those issues could arise on retrial.
La Noue was the developer and the general contractor of the Montara townhouses. La Noue developed the property between 1999 and 2004, and Sharabarin began his work in March 2001. The Montara townhouses consist of nine buildings with three or four units in each building. In 2005, the Montara Owners Association (homeowners) filed a complaint alleging multiple claims against La Noue, seeking to recover for property damages caused by defects in the design and construction of the Montara townhouses. In their breach of contract claim against La Noue, the homeowners alleged that La Noue had contracted with subcontractors to employ and supervise all labor for construction and maintenance of the 35 Montara townhouse units. The homeowners alleged that the building envelope systems failed in all nine buildings, causing water intrusion, water damage, rot, and structural and other physical damage to the units as a result of faulty workmanship, improper or defective materials, improper construction, and noncompliance with building codes. The homeowners further alleged that the defects were so pervasive that all siding, windows, and roofs would have to be removed and repaired. The homeowners asserted a variety of tort and contract claims and a claim under the Unlawful Trade Practices Act, ORS 646.605 to 646.656, against La Noue. The homeowners sought close to $7.5 million in damages, prejudgment interest for the cost of repairing the buildings, and other unspecified damages, including special assessments, loss of profits on the townhouses that had or would be sold, and expenses for loss of use of the townhouses.
La Noue generally denied the homeowners' allegations supporting their claims, and, in response to the claims of damage to the buildings, La Noue brought third-party claims against, among others, more than 20 subcontractors that had provided excavation, fireplaces and chimneys, handrails, framing, gutters, roof trusses, roofing, siding, and other services. Sharabarin is one of those subcontractors, having installed siding on buildings 10 through 13. La Noue alleged negligence, breach of contract, common law and contractual indemnity, and contribution claims against all the subcontractors. Specifically, against Sharabarin and the other siding subcontractors, La Noue alleged a strict products liability claim. For its breach of contract and negligence claims, La Noue alleged that Sharabarin and other subcontractors breached their contractual obligations and failed to perform their work with reasonable care, in a manner consistent with
La Noue then filed a second amended third-party complaint limited to five remaining nonsettling subcontractors, including Sharabarin. Sharabarin's amended answer and affirmative defenses alleged that he performed all work in accordance with the plans and specifications that La Noue and its architects provided to him, and that the work Sharabarin performed was under the supervision and authorization of La Noue's site superintendents. Thus, Sharabarin argued, he was not liable in any respect. La Noue replied, denying Sharabarin's amended answer and affirmative defenses.
As a result of various pretrial rulings, the only claim the trial court submitted to the jury was La Noue's breach of contract claim against Sharabarin and two framers. As relevant to this appeal, before trial, the court granted summary judgment to Sharabarin on La Noue's contractual indemnity claim, ruling that the indemnity clause in La Noue's contract with Sharabarin was void under ORS 30.140.
Trial began in September 2007. At trial, La Noue alleged damages of over $2 million. Sharabarin moved for a directed verdict limiting damages on the breach of contract claim. The court granted, in part, the motion to limit damages. During trial, two additional subcontractors settled with La Noue, leaving only the claims against Sharabarin and two framers. The jury found in favor of La Noue on the breach of contract claim against Sharabarin and the two remaining framers, and it awarded damages against Sharabarin in the amount of $43,711 and against the remaining framers in the amount of $102,101.
In a bench trial three weeks later, the trial court ruled that La Noue could not recover its attorney fees as consequential damages. Meanwhile, the homeowners began repairs. In November 2007, the homeowners were notified of a $900,000 shortfall for repairs. La Noue filed a motion for a new trial under ORCP 64, alleging additional damages, including window damage, damages resulting from a requirement by the City of Portland for building permits, and damages from other unforeseen difficulties causing an extension of the remediation efforts. The court denied La Noue's motion for a new trial, and La Noue filed this appeal. The two remaining framers settled with La Noue while this appeal was pending and La Noue's appeal now solely concerns its claim against Sharabarin.
We begin with La Noue's assertion in its first assignment of error that the trial court erred in instructing the jury on the measure of damages with regard to the breach of contract claim. The parties submitted proposed jury instructions to the trial court. Sharabarin's requested instruction on the measure of damages tracked the language in Uniform Civil Jury Instruction (UCJI) 65.18 for expectation, or "benefit of the bargain," damages:
In contrast, relying on Beik v. American Plaza Co., 280 Or. 547, 555-56, 572 P.2d 305
At the close of evidence, the court instructed the jury that, as to damages, it could choose between the cost of repair and the diminished value of the properties, depending on whether the jury found "undue" or "gross" economic waste. The court's jury instruction on the measure of damages was worded almost exactly as requested by the framer subcontractors and pertained to both the framing and the siding work:
The court did not instruct the jury regarding what "economic waste" meant. La Noue took exception to the instruction.
On appeal, La Noue makes two arguments concerning the jury instruction on damages, asserting that the instruction misstated the applicable law and should not have been given due to a lack of evidence in the record to support the jury instruction.
We review a trial court's decision whether to give an instruction for errors of law. See State v. Barnes, 329 Or. 327, 333-34, 986 P.2d 1160 (1999) (applying that standard of review). For the reasons that follow, we agree with La Noue that the court erred in instructing the jury. Assuming that Sharabarin might have been able to present to the jury an alternative to normal expectation damages based on the economic waste doctrine, he bore the burden of proving the amount of damages the jury should award if it applied that doctrine, namely, the diminished value of the townhouses. McComb v. Cogswell, 140 Or. 676, 15 P.2d 716 (1932).
"Under Oregon law, there are two different types of error respecting jury instructions: (1) error in the failure to give a proposed jury instruction, and (2) error in the jury instructions that actually were given." Williams v. Philip Morris Inc., 344 Or. 45, 55, 176 P.3d 1255 (2008). This case concerns the latter type of instructional error. When we are deciding "whether it was error to give a particular instruction, we read the instructions as a whole to determine whether they state the law accurately." State v. Woodman, 341 Or. 105, 118, 138 P.3d 1 (2006). "[A]s a general rule, the parties in a civil action are entitled to jury instructions on their theory of the case if their requested instructions correctly state the law, are based on the current pleadings in the case, and are supported by evidence." Hernandez v. Barbo Machinery Co., 327 Or. 99, 106, 957 P.2d 147 (1998).
In a breach of contract claim, expectation damages — that is, the amount of a party's expectancy had the contract been fulfilled — are recoverable, if proven. Metropolitan Property & Casualty v. Harper, 168 Or.App. 358, 369, 7 P.3d 541 (2000). "The rule in Oregon is that the cost of replacement or repair is the correct measure of damage for defects in work unless that remedy generates undue economic waste." Beik, 280 Or. at 555, 572 P.2d 305. If the cost of repair is disproportionate to the value of the project, the court will look at the standard of difference in value. Id. In that situation, the proper measure of damages is the difference between the value of the project as properly constructed and its value as actually constructed. Id. at 556 n. 3, 572 P.2d 305.
La Noue contends that, as a general contractor, it was entitled to obtain the cost of replacement or repair from Sharabarin, and that the trial court erred by instructing the jury that, if it concluded that "cost of repair" damages would generate "undue economic waste," the correct measure of damages on La Noue's breach of contract claim against Sharabarin is to be based on the diminished value of the townhouses. La Noue initially asserts that the instruction given was categorically incorrect because the cost of replacement or repair is the correct measure of damages. As previously noted, La Noue asks this court to create an exception to the economic waste doctrine where the dispute
La Noue relies on Metropolitan Property & Casualty, 168 Or.App. at 369, 7 P.3d 541, and cases from other jurisdictions, for the proposition that a general contractor is entitled to recover from a breaching subcontractor the cost of work the general contractor was required to perform as a result of the subcontractor's defective performance. Although Metropolitan Property & Casualty contains a general discussion of contract remedies, La Noue's cases from other jurisdictions involve construction contract damages and support La Noue's argument. For example, in Harmony at Madrona Park Owners Ass'n v. Madison Harmony Dev., Inc., 143 Wn.App. 345, 177 P.3d 755, 762, rev. den., 164 Wn.2d 1032, 196 P.3d 139 (2008), the general contractor was allowed to recover the cost to repair and replace defects within the subcontractor's scope of work, even when the repairs necessitated removal of work by other subtrades.
La Noue further argues that the doctrine of economic waste is simply inapplicable on these particular facts. La Noue explains that it had settled with the homeowners, and the homeowners were, in fact, repairing their property. Because the purpose of the economic waste doctrine is "to limit damages recoverable for a contractor's defective work to those costs necessary to achieve the owner's contract `expectancy' and design intent without unjust enrichment or betterment of the work," Philip L. Bruner and Patrick J. O'Connor, Jr., 6 Bruner and O'Connor on Construction Law § 19:30 (West 2010), La Noue contends that there was no chance of unjust enrichment and the economic waste doctrine simply did not apply. Thus, in La Noue's view, the jury instruction on the measure of damages was an incorrect statement of the law. La Noue further asserted at oral argument that, if a subcontractor can raise the economic waste doctrine in a dispute with a general contractor who has settled, there is no motivation for the subcontractor to engage in settlement negotiations.
Sharabarin responds that the instruction correctly stated Oregon law. Again, that instruction allowed the jury to award damages based on the diminished value of the buildings if the jury found that, "except for technical, nonsubstantial, or immaterial departures by the defendants from the plans and specifications, the framing or siding work is satisfactory, and that an award to [La Noue] for claimed repair costs would result in gross economic waste." He argues that La Noue could receive expectation damages, the normal contract remedy, only if the remedy was prudent — in other words, if the remedy would not create economic waste. Sharabarin explains that, because "economic waste" refers either to a cost of repair that is "disproportionate to the end to be attained" or to a defect that cannot be fixed "without endangering unduly other parts of the building," Beik, 280 Or. at 556 n. 3, 572 P.2d 305, the instruction in this case accurately reflected Oregon law. Sharabarin also argues that there was some evidence to support his theory that awarding the cost of repairs would result in economic waste.
La Noue responds that different legal principles apply to determine damages in contract disputes between general contractors and subcontractors. La Noue urges that we adopt a per se rule that a general contractor is immune from a subcontractor's contention that, due to gross economic waste, damages must be measured by the diminished value of the structures affected by the subcontractor's substandard work. We acknowledge that, as La Noue points out, commentators or treatises on contract law provide that the proper rationale for the economic waste doctrine is to prevent unjust enrichment. See Carol Chomsky, Of Spoil Pits and Swimming Pools: Reconsidering the Measure of Damages for Construction Contracts, 75 Minn L Rev 1445 (1991); J. Calamari & J. Perillo, The Law of Contracts § 14-9 (2d ed 1977). However, the problem for La Noue is that it does not take issue with any particulars of the jury instruction the trial court gave. For example, La Noue does not contend that the absence of any definition of "economic waste" in the instruction, much less one that was consonant with La Noue's understanding of that term, rendered the instruction incorrect on the law. More importantly, we are not persuaded by
Second, La Noue argues that, even if the instruction correctly stated the law in the abstract, it was erroneous to give it in this case in light of the evidence at trial. La Noue contends that there was no evidence at trial from which the jury could determine economic waste or diminished value. Viewing the evidence "in the light most favorable to the establishment of the facts necessary to require giving the requested instruction," Hernandez, 327 Or. at 101 n. 1, 957 P.2d 147, we conclude that La Noue is correct.
La Noue asserts a three-part argument that there was no evidence that would justify giving the instruction. Because we find it dispositive, we discuss only one part of La Noue's argument, which is that there was no evidence at trial of the diminished value of the townhouses as a result of the defects.
Sharabarin does not respond directly to La Noue's characterization of the evidence at trial. Indeed, Sharabarin does not, and cannot, argue that there was evidence at trial establishing the difference between the value of the buildings as constructed and as they should have been constructed. Instead, Sharabarin contends that we must affirm because La Noue bore the burden of proof, at all times, to establish its damages and cannot now complain that the evidence was insufficient. Sharabarin also again argues that there was some evidence of economic waste to support the giving of the damages instruction.
"It is well settled that [a] plaintiff is not required to prove the amount of his damages with mathematical certainty. [The plaintiff] need only establish the fact of damage and evidence from which a satisfactory conclusion as to the amount of damage can be reached." North Pacific Lbr. v. Moore, 275 Or. 359, 366, 551 P.2d 431 (1976). However, because Sharabarin, as the defendant, was arguing for an instruction on a different measure of damages, the diminished value of the townhouses, he had the burden to show that there was a sufficient evidence to establish the amount of damages under that measure. Here, however, there was no evidence in the record that would allow a jury to reach any conclusion as to the diminished value of the townhouses. Testimony by Sharabarin's expert, Scott, is devoid of an assessment of the diminished value of the units as built. His testimony does not address the value of the units. Instead, Scott testified that the scope of Sharabarin's responsibility was but a fraction of the scope of the repairs needed — without identifying what that fraction might be.
We further conclude that the instructional error was not harmless. "[W]hen a trial court incorrectly instructs the jury on an element of a claim or defense and when
La Noue's fourth and fifth assignments of error challenge the trial court's directed verdict limiting the amount of damages that La Noue could seek from Sharabarin on its breach of contract claim.
La Noue's claims for damages are complicated by the role of its insurer, Zurich Financial Services (Zurich), in the collection of payments from the settling subcontractors and Zurich's allocation of payments to the homeowners from Zurich's affiliate insurance companies and the trust accounts established by La Noue's attorneys for that purpose. Against La Noue's asserted damages of $5 million, the trial court granted a partial directed verdict reducing the amount of damages the jury could award La Noue on the breach of contract claim by $1,304 million, the entire amount collected from settling subcontractors. In addition, as to Sharabarin, the trial court granted a partial directed verdict reducing the amount of damages the jury could award La Noue by $833,333, the portion of La Noue's settlement with the homeowners that was paid by Zurich for a period of time before Sharabarin began work on his part of the Montara project in March 2001. Those offsets to the amount of damages that La Noue could seek from Sharabarin, $1,304 million and $833,333, were in addition to a $1 million reduction that La Noue does not challenge on appeal.
The relevant facts, viewed in a light most favorable to La Noue, the party opposing the motion for directed verdict, GPL Treatment, Ltd. v. Louisiana-Pacific Corp., 323 Or. 116, 118, 914 P.2d 682 (1996), are as follows. La Noue's insurer, Zurich, determined that there was coverage for the homeowners' claims under La Noue's policies with Zurich. Zurich decided that there was coverage for four policy years: April 25, 1999, to April 25, 2000; April 25, 2000, to April 25, 2001; April
Zurich paid its $4 million obligation through a series of checks from various affiliate insurance companies that covered La Noue's policies. Zurich directed the settling subcontractors to send settlement payments to La Noue's attorneys, who collected the settlement amounts from the other subcontractors in a trust account and issued payment of those amounts on Zurich's behalf to the homeowners. The sum of the checks issued from the attorneys' trust account and the checks issued by Zurich equaled $4 million. Zurich's direct payments consisted of four checks. Zurich, on behalf of Assurance Company of America, issued a check in the amount of $833,333. The check stub indicates a date of loss within the policy period from April 1999 to April 2000. On behalf of Maryland Casualty Company, Zurich issued a second check in the amount of $833,333; the check stub indicates a date of loss on a policy covering the time period from April 2000 to April 2001. Zurich's third and fourth checks, also written on behalf of Maryland Casualty Company, were in the amount of $833,333 and $196,000. The check stubs indicate a date of loss for the policy covering the time period from April 2001 to April 2002. However, Zurich's major claims unit consultant testified that the notations on the check stubs were not always correct and that sometimes Zurich reallocated losses to the proper policies. Sharabarin began working on his part of the project in March 2001, which is after the time period covered by some of the insurance policies.
At the close of La Noue's evidence at trial, Sharabarin moved for a directed verdict on damages. The court reserved decision until the close of all the evidence. At the close of all the evidence, Sharabarin renewed its motion for a directed verdict and requested dismissal of La Noue's breach of contract claim and partial directed verdicts as to portions of the damages that La Noue could seek from the jury. Because the trial court allowed the breach of contract claim to go to the jury, the court implicitly denied Sharabarin's motion seeking outright dismissal of the breach of contract claim. However, the trial court granted two of Sharabarin's motions directed to portions of the damages La Noue claimed.
As relevant to this appeal, Sharabarin first contended that, as to the monies received from the settling subcontractors, Zurich had no right of subrogation-that is, it had no right to stand in La Noue's shoes and collect those amounts, because the settlement amounts were paid to the homeowners directly, not by Zurich, and because Zurich had failed to properly demonstrate its right to subrogation. Sharabarin also argued that he should not be required to reimburse Zurich for any amounts that subcontractors had already paid because he was not responsible for those losses. The trial court agreed with Sharabarin that he was entitled to an offset of $1.304 million, the total amount the settling subcontractors paid, against the $5 million settlement with the homeowners, and the trial court granted Sharabarin's motion for a directed verdict as to that part of La Noue's claim. La Noue assigns error to that ruling in its fourth assignment.
The trial court also concluded that La Noue could obtain damages from Sharabarin only to the extent that Zurich paid settlement funds to the homeowners on policies that covered the time period that Sharabarin worked on the property, that is, work performed beginning March 2001. The trial court granted Sharabarin's motion for a directed verdict as to $833,333 of La Noue's claimed damages because it concluded that La Noue's insurer paid that amount on an Assurance Company policy that was in effect for a time period before Sharabarin's commencement of work on the Montara buildings. La Noue assigns error to that ruling in its fifth assignment.
This court reviews the grant of a directed verdict for errors of law. GPL Treatment, 323 Or. at 118, 914 P.2d 682. A directed verdict is proper if the pleadings are not sustained by the evidence or reasonable
As to the fourth assignment of error, La Noue asserts multiple arguments about why the trial court erred in determining that Zurich could not recover the $1.304 million recovered from the other settling subcontractors. La Noue contends that it was entitled to repair or expectation damages from Sharabarin, who was liable for the full amount of the damages he caused by his own breach; what other subcontractors paid to settle claims for the separate damages they had caused to the buildings by virtue of breaching their own contracts was immaterial. In addition, La Noue contends that there was, at least, a factual question regarding whether Zurich had paid that amount. Therefore, La Noue concludes that the trial court erred when it granted a directed verdict that reduced Zurich's potential recovery by the amounts the settling subcontractors had paid. For his part, Sharabarin maintains that Zurich did not pay the homeowners the amounts that the settling subcontractors had paid.
We conclude that the trial court erred in reducing the total amount that Zurich could recover through subrogation by the settlement amounts Zurich received from other subcontractors. The uncontroverted evidence was that Zurich had paid $4 million to settle with the homeowners. The fact that Zurich chose to send direct payments from the settling subcontractors to an attorney trust account and to have some of the settlement payments to the homeowners paid from that account, as opposed to another bank account containing Zurich's funds, does not change Zurich's $4 million settlement payment to the homeowners.
Nor did Zurich's receipt of settlement payments from other subcontractors, who performed other work on the Montara buildings, offset damages that Sharabarin caused by breaching his contract with La Noue. The evidence at trial established that Sharabarin was the siding subcontractor on a group of the Montara buildings. Sharabarin has not articulated any factual basis to conclude that his work and the damages he caused as a result of his breach of contract were duplicative of the work or damages caused by other subcontractors who settled with La Noue. In fact, at trial, Sharabarin acknowledged that there was no evidence that the settlement amounts paid by other subcontractors was for damages that Sharabarin might have caused. Thus, La Noue should have been allowed to recover its damages from Sharabarin — alleged to be in excess of $2 million — without regard to what other subcontractors paid to settle claims with La Noue.
Turning to the fifth assignment of error, La Noue challenges the directed verdict as to the $833,333 payment under the Assurance Company policy, which covered the period from April 1999 to April 2000. La Noue contends that there was no evidence to establish the significance of Zurich's internal decisions to allocate the settlement obligation with the homeowners among La Noue's policies, particularly as to the time period that a check was intended to cover. Sharabarin, however, points to the fact that the Assurance Company policy provided coverage for a timeframe before he began work on the Montara buildings in March 2001 and to Zurich's check on behalf of Assurance Company, which it appears was written for losses during the April 1999 to April 2000 period. That evidence, we conclude, supports the trial court's ruling, because Sharabarin could not have been responsible for covered losses during that timeframe. We also reject La Noue's suggestion that Zurich should be able to recover for payments it made for losses during a time period when Sharabarin did not perform work on the buildings to encourage settlements. See Colonial Penn Ins. Co. v. Aery, 112 Or.App. 87, 89, 827 P.2d 933 (1992) ("`Subrogation is the right of the insurer to be put in the position of the insured in order to pursue recovery from third parties legally responsible to the insured for a loss paid by the insurer.' 16 Couch On Insurance 75, § 61.1 (2d ed. 1983).").
La Noue sought over $2 million in damages at trial, which the trial court capped at $1,862,666 after making offsets of $1 million, $1.304 million, and $833,333 from the $5 million settlement with the homeowners. Because
In its third assignment of error, La Noue asserts that the trial court erred in granting Sharabarin's motion to dismiss La Noue's contractual indemnity claim on the ground that ORS 30.140 renders the parties' contractual indemnification agreement void in its entirety. La Noue contends that the court did not correctly interpret ORS 30.140 and that, under the language of the statute, the indemnity clause is not void but merely unenforceable in part. Sharabarin asserts that the trial court correctly interpreted ORS 30.140 and, therefore, properly entered summary judgment against La Noue on its indemnity claim against Sharabarin.
The indemnity clause in the La Noue/Sharabarin subcontract provided:
Under the indemnity clause, Sharabarin was required to indemnify La Noue for any loss arising out of Sharabarin's work "whether or not caused in part by" La Noue itself, except if the loss was caused by La Noue's "sole" negligence. Thus, the clause required Sharabarin to indemnify La Noue for any loss arising out of Sharabarin's work, even if the loss was caused in part by La Noue's negligence.
The trial court ruled that the indemnity clause was void under ORS 30.140, which provides, in part:
The parties agree that the indemnity clause in the La Noue/Sharabarin subcontract does what ORS 30.140(1) prohibits: it requires Sharabarin to indemnify La Noue for losses caused in part by La Noue. Because the court determined that the indemnity clause is void under ORS 30.140, it granted Sharabarin's motion for summary judgment on the indemnity claim. La Noue asserts, in its third assignment of error, that the court erred because it misinterpreted the statute.
"On review of a summary judgment, we determine whether the moving party is entitled to judgment as a matter of law." Moore v. Mutual of Enumclaw Ins. Co., 317 Or. 235, 237, 855 P.2d 626 (1993). Because this is an issue of statutory interpretation, we apply our usual framework. To interpret ORS 30.140, we examine the text and context of the statute, in light of any useful legislative history offered by the parties. State v. Gaines, 346 Or. 160, 171-72, 206 P.3d 1042 (2009). Context includes other provisions of the statute. Owens v. Maass, 323 Or. 430, 435-36, 918 P.2d 808 (1996). We may not insert what has been omitted, or omit what has been inserted. ORS 174.010. If possible, we must give effect to all of a statute's provisions. State v. Hernandez, 186 Or.App. 86, 90, 61 P.3d 951 (2003).
The core issue of statutory construction here is whether, as La Noue contends, ORS 30.140(2) states an exception to subsection
In Sharabarin's view, subsection (2) does not save or allow partial enforcement of an indemnity clause that otherwise violates subsection (1) and is void. Rather, Sharabarin contends that the two subsections describe two types of indemnity clauses-one that fails and one that is enforceable: Subsection (1) describes those clauses that are void because they require indemnity of a person for damages caused in whole or in part by the person's own negligence. Subsection (2) describes those clauses that are enforceable because they provide for indemnity to a person for damages caused by the fault of the indemnitor.
Under Sharabarin's interpretation, an indemnity clause may require a subcontractor to indemnify the general contractor for property damage caused by the subcontractor's negligence. But it cannot require a subcontractor to indemnify the general contractor for claims for property damage caused by the fault of the subcontractor and also by the fault of the general contractor or by the fault of the general contractor and some other third party. In other words, subsection (1) relates to indemnity clauses that allow indemnity claims for damages not caused by the indemnitor and caused either solely or partially by the general contractor, and those are void. Subsection (2) relates to indemnity clauses that allow indemnity claims for damages caused by the indemnitor and not by the general contractor/indemnitee, and those are enforceable.
Sharabarin asserts that an indemnity clause that does what subsection (1) prohibits cannot be saved because it also does what subsection (2) permits: if the clause requires a subcontractor to indemnify a general contractor for the general contractor's negligence, then the clause is void, despite the fact that it also does what subsection (2) permits by permitting indemnity for the indemnitor's own negligence. In Sharabarin's view, this is the only way to construe the two subsections together and consistently with each other.
Further, in Sharabarin's view, the indemnity clause at issue here fails because, although it does what ORS 30.140(2) allows, by requiring Sharabarin to indemnify La Noue for claims caused by the fault of Sharabarin, it also does what ORS 30.140(1) prohibits, by requiring Sharabarin to indemnify La Noue for claims caused in part by the fault of La Noue.
La Noue replies that Sharabarin's interpretation is not the only way to construe the two provisions harmoniously, and that, in fact, the provisions work more harmoniously together if subsection (2) is understood as an exception to subsection (1): Those portions of an indemnity clause that violate subsection (1) are void and those portions that are consistent with subsection (2) will be enforced. La Noue notes that, in Hays v. Centennial Floors, Inc., 133 Or.App. 689, 695, 893 P.2d 564 (1995), this court previously construed ORS 30.140 and has permitted partial enforcement of an indemnity provision that violates ORS 30.140 to the extent that its application requires the subcontractor
As Sharabarin correctly points out, Hays construed a former version of the statute. Before it was amended by Oregon Laws 1995, chapter 704, section 1, ORS 30.140 provided:
Subsequent to Hays, the legislature amended the statute to its current form. We provided a description of those changes in our opinion in Walsh Construction Co. v. Mutual of Enumclaw, 189 Or.App. 400, 407-08, 76 P.3d 164 (2003), aff'd, 338 Or. 1, 104 P.3d 1146 (2005) which the Supreme Court adopted in its own opinion in that case. Specifically, the Supreme Court stated:
338 Or. 1, 8-9, 104 P.3d 1146 (2005) (some internal quotation marks omitted; footnote omitted). In Walsh, this court concluded
The question is presented here, because La Noue contends that Sharabarin's work was defective. Thus, we must decide whether an indemnity clause that includes provisions allowed by ORS 30.140(2) is nonetheless unenforceable because it also includes provisions prohibited by ORS 30.140(1). The question is a close one. As noted earlier, the "[e]xcept to the extent provided under subsection (2)" clause could suggest that an indemnity clause that is void because it violates subsection (1) is not void to the extent that it complies with subsection (2). Or, it could be understood to mean that indemnity clauses that include provisions described in subsection (1) are void, and indemnity clauses including provisions described in subsection (2) are enforceable.
Ultimately, we conclude that La Noue's interpretation of the statute is more persuasive, primarily because Sharabarin's interpretation would render superfluous the clause in subsection (1) that such provisions are void "except to the extent provided in subsection (2)." That language allows an indemnity clause to be enforced to the extent that it allows for indemnity for damage to property caused by the indemnitor, such as the clause in this case. An indemnity clause that offends ORS 30.140(1) because it requires a subcontractor to indemnify a contractor for the contractor's own negligence remains enforceable to the extent that it also requires the subcontractor to indemnify the contractor for the subcontractor's negligence. Because the indemnity clause in the La Noue/Sharabarin contract requires Sharabarin to indemnify La Noue for claims based on its own fault, it is enforceable to that extent. The trial court therefore erred in granting Sharabarin's motion for summary judgment on the indemnity claim, and we remand on that claim.
In its sixth assignment of error, La Noue asserts that the trial court erred in concluding that attorney fees were not recoverable as consequential damages and in granting judgment as a matter of law on La Noue's claim for attorney fees and costs. Sharabarin responds that, under ORCP 68, the trial court correctly held that La Noue could not recover attorney fees as part of its consequential damages on the breach of contract claim. We agree with Sharabarin.
La Noue relies on Huffstutter v. Lind, 250 Or. 295, 301, 442 P.2d 227 (1968), to argue that "attorney fees are generally allowable as damages in an action against a defendant where the defendant's tortious or wrongful conduct involved the plaintiff in prior litigation with a third party." But here, there is no prior litigation with a third party-the fees that La Noue seeks to recover are fees it incurred in defending the case at issue. Thus, the recovery of those fees is subject to ORCP 68, which governs the award of attorney fees in all cases except when they are "claimed as damages arising prior to the action" or the fees are granted by order, rather than entered as part of a judgment. ORCP 68 C(1); see also State v. O'Brien, 96 Or.App. 498, 505, 774 P.2d 1109 (1989) ("Attorney fees are not considered damages when sought in the same action in which the services are rendered. However, they may be damages when sought in a separate action."). Because the fees do not originate from prior litigation with a third party, the court did not err in denying La Noue's request for attorney fees.
The trial court erred in giving a jury instruction on damages based on diminished value when there was no evidence in the record to support the instruction. The trial court erred in limiting the damages La Noue could recover to $1,862,666, but the trial court correctly held that the amount of damages La Noue sought could not include any sum received from Zurich for a time period before Sharabarin began work at Montara. The trial court erred in holding the indemnity clause in the parties' contract void. We therefore remand for a new trial on damages only. The trial court's denial of attorney fees is affirmed.
Reversed and remanded on claims for breach of contract and indemnity; otherwise affirmed. Motion for remand denied.
NAKAMOTO, J., concurring.
We hold, contrary to the customary burden of proof, see North Pacific Lbr. v. Moore, 275 Or. 359, 366, 551 P.2d 431 (1976), that third-party defendant Sharabarin — not third-party plaintiff La Noue Development, LLC had the burden to establish the amount of damages that La Noue could recover under the alternative measure of damages that Sharabarin argued should apply. 259 Or.App. at 665 n. 3, 317 P.3d at 263 n. 3. Although I agree that Sharabarin was required to establish the amount of the diminution in value of the buildings, I disagree with the majority's reasoning.
The majority explains the rationale for the holding as follows:
Id. I write separately to note that (1) McComb v. Cogswell, 140 Or. 676, 15 P.2d 716 (1932), can be read to support our holding, but not in the way the majority describes, and (2) cases from other jurisdictions support our conclusion that Sharabarin bore the burden to adduce evidence of the diminished value of the Montara buildings.
Initially, I disagree that McComb suggests that the correct measure of damages in a case "where it is alleged that a party failed to build a building in accordance with the contract," 259 Or.App. at 665 n. 3, 317 P.3d at 263 n. 3, is diminished value rather than cost of repairs. The normal measure of damages in such a case is cost of replacement or repair. In Beik v. American Plaza Co., 280 Or. 547, 555, 572 P.2d 305 (1977), the Supreme Court stated the "rule in Oregon" as follows: "the cost of replacement or repair is the correct measure of damage for defects in work unless that remedy generates undue economic waste."
In addition, the majority suggests that McComb is a "failure of proof case on the part of a proponent of "diminished value" damages. But the defendant homeowners in McComb, who had filed a counterclaim and sought damages for breach of the construction contract, had not contended that the proper measure of damages was diminished value. Rather, they attempted to establish the normal measure of damages due to the plaintiff contractor's departures from the plans and specifications in their contract through testimony from an expert as "to what it would cost to replace or reconstruct according to contract." 140 Or. at 679, 15 P.2d 716. The Supreme Court, however, noted
Nevertheless, McComb may still lend support to the conclusion that Sharabarin had to adduce evidence of the amount of the diminished value of the buildings at trial. That is because of the Supreme Court's emphasis on the pleadings and facts. McComb may suggest that notice to a party that an alternative measure of damages could apply is important. Here, Sharabarin did not plead that the economic waste doctrine applied, and his own proposed jury instruction would have allowed La Noue to obtain typical damages for a breach of contract, that is, expectation damages.
La Noue also relies on cases from other jurisdictions, such as Panorama Village Homeowners v. Golden Rule, 102 Wn.App. 422, 428, 10 P.3d 417, 422 (2000), rev. den., 142 Wn.2d 1018, 16 P.3d 1266 (2001), and Andrulis v. Levin Constr. Corp., 331 Md. 354, 376, 628 A.2d 197, 208 (1993), for the proposition that, once it established the cost to remedy the defects that Sharabarin caused, Sharabarin was required to come forward with evidence of the diminished market value of the buildings. La Noue's position appears to be the majority view. See also Shell v. Schmidt, 164 Cal.App.2d 350, 366, 330 P.2d 817, 827 (1958), cert. den., 359 U.S. 959, 79 S.Ct. 799, 3 L.Ed.2d 766 (1959); P.G. Lake, Inc. v. Sheffield, 438 S.W.2d 952, 956 (Tex.Ct.Civ.App.1969); Stangl v. Todd, 554 P.2d 1316, 1320 (Utah 1976). Although the contours of the economic waste doctrine in Oregon are not as specifically defined as in cases from other jurisdictions, such as Andrulis, given the present circumstances, where Sharabarin did not make it evident that he was going to rely on the economic waste doctrine at trial, I concur that Sharabarin bore the burden to produce evidence of the diminution in the value of the buildings before the jury was instructed on his theory of damages. As the majority opinion explains, that proof was lacking, and so giving the damages instruction was error.